Exact material quantities with the formula shown, so you can check the math yourself. Concrete, framing, roofing and electrical rough-in.

✓ No prices invented. You enter your own supplier cost. A national average that doesn't match your yard is worse than none.

Result
 

    This is one number. A bid needs a few hundred.

    You just did one assembly by hand. Send one sheet of the same job and we count every material on it, free, back by 8am. No card, no call.

    Send one sheet, free

    Questions contractors actually ask

    How many cubic yards of concrete do I need for a slab?

    Length × width × thickness, all in feet, divided by 27. A 4″ slab is 0.333 ft thick. So a 20×30 slab at 4″ is 20 × 30 × 0.333 = 200 cu ft ÷ 27 = 7.4 cubic yards. Add 5 to 10% waste and order 8.

    How much waste should I add to a concrete order?

    5% on a well-prepared slab over compacted gravel with tight forms. 10% on footings, uneven subgrade, or anywhere the forms might bulge. Ready-mix sells in quarter-yard increments, and short-loading a pour costs far more than the extra yard.

    How many studs do I need for a wall?

    Wall length in inches ÷ on-center spacing, plus one for the end. A 40 ft wall at 16″ OC is 480 ÷ 16 = 30, +1 = 31 studs. Then add 2 per corner and 2 to 3 per opening for kings and jacks, plus headers.

    How many squares of shingles do I need?

    A square is 100 sq ft. Roof area is footprint × pitch factor: 6/12 is 1.118, 8/12 is 1.202, 12/12 is 1.414. Architectural shingles run 3 bundles per square. Add 10% for hips, valleys and starter.

    How many electrical circuits does a house need?

    NEC 220.12 sets general lighting load at 3 VA per sq ft for dwellings. A 2,400 sq ft house is 7,200 VA ÷ 120 V = 60 A, so four 15 A general lighting circuits minimum. Then the NEC requires at least two 20 A small-appliance circuits, one 20 A laundry, one 20 A bathroom, plus dedicated circuits for fixed appliances.